Project Description
Renovate Charlotte County Administration Center, Murdock Campus, Building D to accommodate the growing needs of the Facilities Construction and Maintenance Department.
Project Location
18500 Murdock Circle, Building-D, Port Charlotte, Florida 33948.Project Impacts
Weather
Florida Department of Environmental Protection
South West Florida Water Management District
Latest Updates
A meeting was held with the Fawley Bryant design team to finalize the construction documents for the Building D renovation project. Fawley Bryant will submit the signed and sealed plans to the Building Department for finalization.
Budget
Phase | Cost |
---|---|
Design | $80,000 |
Construction | $800,000 |
Total Budget | $880,000 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Planning and Approval | 06/08/2023 | 01/30/2024 | |
Design Development | 04/02/2024 | 10/01/2024 | |
Construction | 10/23/2024 | 10/23/2025 | |
Turnover & Closeout | 10/31/2025 | 12/01/2025 |
Project Phase
Design Development
Last Updated
10/25/2024
Project Manager
Pedro Agosto
Public Relations
Brian Gleason
Email Public Relations
Project Number
c192201
Sponsor Department
Facilities
Design Engineer/Architect
Fawley Bryant
Construction Contractor
TBD