Project Description
William R. Gaines Jr. Veterans Memorial Park Phase II design and construction will include one (1) large pavilion, three (3) bocce ball courts with shade canopies, two (2) pickleball courts with lights, one (1) tennis court with lights, and sanitary utility connection to the existing park restroom.
Project Location
William R. Gaines Jr. Veterans Memorial Park
20499 Edgewater Dr.
Port Charlotte, Florida 33952
Project Impacts
Inclement weather
Protected Species
Supply chain delays
Budget
Phase | Cost |
---|---|
Construction | $1,750,000 |
Total Budget | $1,750,000 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Design Development | 03/12/2024 | 03/12/2025 | |
Construction | 04/09/2024 | 05/29/2026 | |
Turnover & Closeout | 05/29/2026 | 06/30/2026 |
Project Phase
Design Development
Last Updated
10/31/2024
Project Manager
Vicki Chichura
Public Relations
Brian Gleason
Email Public Relations
Project Number
c722106
Sponsor Department
Community Services
Design Engineer/Architect
Kimley-Horn
Construction Contractor
Jon F. Swift Construction