Ackerman Wastewater Expansion

Project Description

The Ackerman Municipal Services Benefit Unit (MSBU) was approved in November 2019. It includes construction of a wastewater collection system to service approximately 1,300 properties with sewer service, new water service lines and a vacuum station that will provide sewer collection for the wastewater system. The project is divided into four zones and a low-pressure sewer (LPS) section.

Learn how MSBUs work at Charlotte County.

For questions about the Ackerman MSBU, contact the Capital Projects Office:

Phone: 941.764.4560
Email: S2S@CharlotteCountyFL.gov.

Project Location

Throughout the Ackerman Avenue neighborhood in Port Charlotte. 

Project Impacts

During construction, residents may experience noise, dust, lane closures or detours, reduced access to driveways or sidewalks and the presence of construction crews and equipment in the area. Utility service interruptions will be communicated in advance and are temporary. We appreciate your patience and cooperation.

Septic system inspection notices are managed by the Florida Department of Health. Visit their website for more information. For information about maintaining a septic system, visit the Florida Department of Environmental Protection.

Latest Updates

Discussion of construction costs are ongoing.  
Vacuum station
  • Construction of the vacuum station located at 18330 Ackerman Ave. is complete.

Zone 1

  • Zone 1 connections were completed on March 13, 2025.

Zone 2

  • Zone 2 connections are underway.
  • Water line replacement and sewer main installation is complete.

Zones 3, 4 and low-pressure sewer (LPS)

  • The Board of County Commission approved Forsberg Construction, Inc. as the contractor for Zones 3, 4 and LPS. Forsberg will install water and sewer infrastructure in this area. After the infrastructure is in place, plumbing contractors will be procured to complete residential connections. 
  • Watermain installation for Zone 4 is underway. Once water main installation is complete, installation of the sewer infrastructure will begin.

Budget

Phase Cost
Total Budget $70,600,000.00
Funding source(s):

Resident Assessments, Florida Department of Environmental Protection State Revolving Funds, EPA Grants, RESTORE, Utility Repair and Replacement Funds.

Schedule

Phase Estimated Start Date Forecast Completion Actual Completion
Planning and Approval 11/19/2019 12/01/2020 12/01/2020
Design Development 01/21/2021 02/01/2022 02/01/2022
Construction 04/05/2021 10/03/2028

Supporting Materials

Ackerman Wastewater Expansion Project Image

Project Phase
Construction

Last Updated
02/26/2026

Project Manager
Colby Rodgers

Public Relations
Stuart Gooden
Email Public Relations

Sponsor Department
Utilities

Design Engineer/Architect
Giffels-Webster Engineers

Construction Contractor
Forsberg Construction, Inc