Ackerman Wastewater Expansion

Project Description

The Ackerman Municipal Services Benefit Unit (MSBU) was approved in November 2019. It includes construction of a wastewater collection system to service approximately 1,300 properties with sewer service, new water service lines and a vacuum station that will provide sewer collection for the wastewater system. The project is divided into four zones and a low-pressure sewer (LPS) section.

Learn how MSBUs work at Charlotte County.

For questions about the Ackerman MSBU, contact the Capital Projects Office:

Phone: 941.764.4305
Email: S2S@CharlotteCountyFL.gov.

Project Location

Throughout the Ackerman Avenue neighborhood in Port Charlotte. 

Project Impacts

During construction, residents may temporarily experience low water pressure.

Latest Updates

Discussion of construction costs are ongoing.  
Vacuum station
  • Construction of the vacuum station located at 18330 Ackerman Ave. is complete.

Zone 1

  • Zone 1 connections were completed on March 13, 2025.

Zone 2

  • Zone 2 connections started on Sept. 22, 2023 and are currently expected to be completed in mid-2026.
  • Water line replacement and sewer main installation is complete.
  • Due to unexpected circumstances beyond our control involving the contractor, there is a delay for customers scheduled for Zone 2 connections. We understand the inconvenience this may cause and remain fully committed to progressing the project as quickly as possible. An update will be provided on this page with information.

Zones 3, 4 and low-pressure sewer (LPS)

  • The Board of County Commission approved Forsberg Construction, Inc. as the contract for Zones 3, 4 and LPS.   
    • Construction in Zone 3 began in March 2025. 
  • Water main installation in the LPS area began the week of Oct. 6.
  • Water main installation in Zone 4 Phase 2 is scheduled for pressure testing Oct. 20 and 21.
  • Water main installation for Zone 4 Phase 1 is awaiting clearance from the Florida Department of Environmental Protection (FDEP).

Budget

Phase Cost
Total Budget $51,693,929.23
Funding source(s):

Resident Assessments, Florida Department of Environmental Protection State Revolving Funds, EPA Grants, RESTORE, Utility Repair and Replacement Funds.

Schedule

Phase Estimated Start Date Forecast Completion Actual Completion
Planning and Approval 11/19/2019 12/01/2020 12/01/2020
Design Development 01/21/2021 02/01/2022 02/01/2022
Construction 04/05/2021 10/03/2028

Supporting Materials

Project Phase
Construction

Last Updated
10/15/2025

Project Manager
Jody Pressley

Public Relations
Stuart Gooden
Email Public Relations

Sponsor Department
Utilities

Design Engineer/Architect
Giffels-Webster Engineers

Construction Contractor
Forsberg Construction, Inc