Project Description
Bermont Road Box Culvert Rehabilitations - This project has four box culverts needing minor repairs to extend their service life.
CR 74 (Bermont Road) over Myrtle Slough - #010003
CR 74 (Bermont Road) over Shell Creek Drainage - #010016
CR 74 (Bermont Road) over Babcock Drainage - #010017
CR 74 (Bermont Road) over Myrtle Slough - #010020
Project Location
CR 74 (Bermont Road) over Myrtle Slough - #010003
CR 74 (Bermont Road) over Shell Creek Drainage - #010016
CR 74 (Bermont Road) over Babcock Drainage - #010017
CR 74 (Bermont Road) over Myrtle Slough - #010020
Latest Updates
Upcoming Project Activities for December 2025
Titan Construction has completed work on the first two box culverts (#010003 and #010020). The contractor is now progressing on the final two box culvert structures, which are expected to be completed by mid-January.
*We are currently processing a change order to extend the contract duration by 30 calendar days. At the start of the project, frequent rain events resulted in significant delays, with all box culverts submerged and inaccessible, preventing progress on critical work activities.
Budget
| Phase | Cost |
|---|---|
| Design | $139,890 |
| Construction | $863,587.20 |
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Design Development | 04/15/2024 | 04/18/2025 | |
| Construction | 09/24/2025 | 01/08/2026 |
Project Phase
Construction
Last Updated
12/16/2025
Project Manager
Kelly Slaughter
Public Relations
Chad Ray
Email Public Relations
Sponsor Department
Public Works Engineering
Design Engineer/Architect
Weiler Engineering Corp
Construction Contractor
Titan Construction


