Charlotte County, FL Logo

941.743.1200
18500 Murdock Circle
Port Charlotte, FL 33948

Mobile Menu close icon
close search

Bermont Road Box Culverts Rehabilitations -Road and Bridge FY24

Project Description

Bermont Road Box Culvert Rehabilitations - This project has four box culverts needing minor repairs to extend their service life.

CR 74 (Bermont Road) over Myrtle Slough - #010003

 CR 74 (Bermont Road) over Shell Creek Drainage - #010016

CR 74 (Bermont Road) over Babcock Drainage - #010017

CR 74 (Bermont Road) over Myrtle Slough - #010020

Project Location

CR 74 (Bermont Road) over Myrtle Slough - #010003

 CR 74 (Bermont Road) over Shell Creek Drainage - #010016

CR 74 (Bermont Road) over Babcock Drainage - #010017

CR 74 (Bermont Road) over Myrtle Slough - #010020

Latest Updates

Upcoming Project Activities for December 2025

Titan Construction has completed work on the first two box culverts (#010003 and #010020). The contractor is now progressing on the final two box culvert structures, which are expected to be completed by mid-January.

*We are currently processing a change order to extend the contract duration by 30 calendar days. At the start of the project, frequent rain events resulted in significant delays, with all box culverts submerged and inaccessible, preventing progress on critical work activities.

Budget

Phase Cost
Design $139,890
Construction $863,587.20
Funding source(s): Road and Bridge Funding

Schedule

Phase Estimated Start Date Forecast Completion Actual Completion
Design Development 04/15/2024 04/18/2025
Construction 09/24/2025 01/08/2026

Project Phase
Construction

Last Updated
12/16/2025

Project Manager
Kelly Slaughter

Public Relations
Chad Ray
Email Public Relations

Sponsor Department
Public Works Engineering

Design Engineer/Architect
Weiler Engineering Corp

Construction Contractor
Titan Construction

Delivering Exceptional Service

Questions? Issues?

Contact Us