Project Description
Bermont Road Box Culvert Rehabilitations - This project has four box culverts needing minor repairs to extend their service life.
CR 74 (Bermont Road) over Myrtle Slough - #010003
CR 74 (Bermont Road) over Shell Creek Drainage - #010016
CR 74 (Bermont Road) over Babcock Drainage - #010017
CR 74 (Bermont Road) over Myrtle Slough - #010020
Project Location
CR 74 (Bermont Road) over Myrtle Slough - #010003
CR 74 (Bermont Road) over Shell Creek Drainage - #010016
CR 74 (Bermont Road) over Babcock Drainage - #010017
CR 74 (Bermont Road) over Myrtle Slough - #010020
Latest Updates
Upcoming Project Activities for October 2025
Titan Construction has started construction on the first two box culverts (#010003 and #010020), these are expected to be completed by mid-November.
Budget
| Phase | Cost |
|---|---|
| Design | $139,890 |
| Construction | $863,587.20 |
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Design Development | 04/15/2024 | 04/18/2025 | |
| Construction | 09/24/2025 | 12/08/2025 |
Project Phase
Construction
Last Updated
10/14/2025
Project Manager
Kelly Slaughter
Public Relations
Chad Ray
Email Public Relations
Sponsor Department
Public Works Engineering
Design Engineer/Architect
Weiler Engineering Corp
Construction Contractor
Titan Construction