Project Description
Design Firm: Harvard Jolly. CM@Risk: TBD. Preliminary drafted site plan showing 1-story and a 2-story option on the north and south side of the existing EOC were presented by the design team to the stakeholders. Stakeholders preferred to go with the one-story/North side of existing building option. The Board approved the CM@Risk rankings and to start negotiations with the top ranked firm, Florida Premier Contractors for this project. Negotiations to start on 6/4/2025, with the top ranked firm.
Project Location
26571 Airport Road, Punta Gorda, Florida 33982.Project Impacts
South West Florida Water Management District
Florida Department of Environmental Protection
Weather
Latest Updates
Design Firm: Harvard Jolly. Construction Manager @ Risk: TBD. The Board approved the Construction Manager @ Risk rankings and to start negotiations with the top ranked firms, for this project.
Florida PC has submitted their proposal to Purchasing on 6/11/2025 for review. FPC’s proposal was reviewed and accepted after some back and forth during negotiations. FPC’s proposal for the EOC will go before the Board on July 22, for approval.
Budget
Phase | Cost |
---|---|
Design | $1,000,000 |
Construction | $11,000,000 |
Total Budget | $12,000,000 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Planning and Approval | 12/12/2023 | 05/12/2025 | 09/06/2024 |
Design Development | 10/01/2024 | 11/27/2025 | |
Construction | 11/27/2025 | 12/30/2026 | |
Turnover & Closeout | 01/21/2026 | 02/25/2026 |
Project Phase
Design Development
Last Updated
07/02/2025
Project Manager
Pedro Agosto
Public Relations
Brian Gleason
Email Public Relations
Project Number
c222404
Sponsor Department
Public Safety
Design Engineer/Architect
Harvard Jolly
Construction Contractor
TBD