Project Description
The project will replace two outdated and undersized buildings constructed in 1992 with a single, more efficient, up-to-date facility. The new facility will meet current safety and storm-resiliency standards and will accommodate increased staffing needs and future growth.Project Location
29751 Zemel Rd
Punta Gorda FL 33955
Latest Updates
The shortlisting to select the design consultant was held January 21st and the ranking will be presented to the Board for approval on February 10thBudget
| Phase | Cost |
|---|---|
| Design | $318,000 |
| Construction | $6,233,000 |
| Other Costs | $130,000 |
| Total Budget | $6,681,000.00 |
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Planning and Approval | 12/24/2025 | 02/10/2026 | |
| Design Development | 02/11/2026 | 10/21/2026 | |
| Construction | 11/26/2026 | 08/07/2027 | |
| Turnover & Closeout | 08/15/2027 | 10/29/2027 |
Project Phase
Planning and Project Approval
Last Updated
02/03/2026
Project Manager
Scott Brouillard
Public Relations
Brian Gleason
Email Public Relations
Project Number
C342601
Sponsor Department
Public Works