Project Description
Remove hurricane debris from approximately 37 miles of navigable waterways througout the county.Project Location
There are various navigable waterway systems that are included in this project.Latest Updates
Work began on March 10, 2026 in the Ainger Creek waterway system.Budget
| Phase | Cost |
|---|---|
| Construction | $800,000 |
| Other Costs | $200,000 |
| Total Budget | $1,000,000.00 |
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Construction | 03/10/2026 | 06/09/2026 |
Supporting Materials
Last Updated
03/13/2026
Project Manager
Karen Bliss
Public Relations
Chad Ray
Email Public Relations
Project Number
2026-072
Sponsor Department
Public Works Engineering
Construction Contractor
Looks Great Services of MS, Inc.