Project Description
The West County Stormwater MSBU has requested this project, which will involve the removal and disposal of all nuisance and exotic vegetation, as well as trash, from approximately 17 acres of Oyster Creek to maintain positive drainage.Project Location
The portion of Oyster Creek that is included in this project starts at McKinley Terrace where the Gondolier Waterway turns into Oyster Creek and continues south under Rt. 776 and Winchester Boulevard into the Oyster Creek Subdivision. The project ends at San Casa Drive.Latest Updates
We are currently seeking permission from a private property owner to access a section of Oyster Creek on their property.Budget
| Phase | Cost |
|---|---|
| Construction | $95,000.00 |
| Total Budget | $95,000.00 |
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Planning and Approval | 11/12/2025 | 12/12/2025 | |
| Construction | 03/02/2026 | 06/01/2026 |
Project Phase
Planning and Project Approval
Last Updated
11/20/2025
Project Manager
Karen Bliss
Public Relations
Chad Ray
Email Public Relations
Sponsor Department
Public Works Engineering
Construction Contractor