Project Description
A Master Developement Order agreement between Charlotte County and the developer has been made to build a new Law Enforcement Office located in southern Charlotte County as part of the Master Babcock Ranch Concept Plan.Project Location
17755 Curry Preserve Drive, Punta GordaProject Impacts
No expected delays or impacts to the project.Latest Updates
Interior wall framing and hollow metal door frames and interior wall insulation done.Some drywall in process, above ceiling fire sprinkler rough completed, above ceiling electrical, mechanical and plumbing wall rough is in progress. Air handler install completed.
Gas meter was installed this week.
Budget
Phase | Cost |
---|---|
Design | $500,000 |
Engineering | $658,741 |
Construction | $2730810 |
Total Budget | $3,677,770 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Planning and Approval | 01/01/2023 | 08/01/2023 | 08/01/2023 |
Design Development | 01/01/2023 | 08/01/2023 | 08/01/2023 |
Construction | 12/01/2023 | 01/01/2025 | |
Turnover & Closeout | 01/01/2025 | 02/11/2025 |
Project Phase
Construction
Last Updated
07/26/2024
Project Manager
Gary Burdahl
Public Relations
Brian Gleason
Email Public Relations
Project Number
c892201
Sponsor Department
CCSO Sheriff's Dept
Design Engineer/Architect
Fawley Bryant Architecture
Construction Contractor
Florida Premier Contractors