Project Description

These 2 bridges currently require design services to implement the FDOT maintenance and repair items for each of the respective bridges.  

Bridge #014049 is Biscayne Drive over the Jupiter Waterway.

Bridge #014050 is Biscayne Drive over the Apollo Waterway.

Project Location

Bridge #014049 is Biscayne Drive over the Jupiter Waterway.

Bridge #014050 is Biscayne Drive over the Apollo Waterway.

Latest Updates

Project Activities April 2025

Bridge #014050 Biscayne Drive over the Apollo Waterway is completed.

Bridge #014049 Biscayne Drive over the Jupiter Waterway, is currently closed for rehabilitation. It is scheduled to reopen on May 22, 2025.  

Budget

Phase Cost
Design $148,960
Construction $813,431
Funding source(s): Road and Bridge Gas Tax

Schedule

Phase Estimated Start Date Forecast Completion Actual Completion
Design Development 01/08/2024 07/12/2024
Construction 02/03/2025 06/03/2025
Turnover & Closeout 02/03/2025 05/09/2025

Project Phase
Construction

Last Updated
04/10/2025

Project Manager
Kelly Slaughter

Public Relations
Chad Ray
Email Public Relations

Sponsor Department
Public Works

Design Engineer/Architect
Weiler Engineering Corp

Construction Contractor
Villa Fuerte Construction