Project Description
The project will add two sidewalks, one on Caring Way, from Olean Boulevard to Gertrude Avenue, and one on Brinson Avenue, from Caring Way to Harbor Boulevard. Additionally, the project will incorporate the removal and replacement of any of Charlotte County Utility Department's (CCUD) infrastructure located under or impacted by the future sidewalks.
The project may be constructed as one or two separate projects, which will be determined before the bid advertisement.
Project Location
Caring Way, from Olean Boulevard to Gertrude Avenue
Brinson Avenue, from Caring Way to Harbor Boulevard
Latest Updates
The PO was issued and the engineer is working on the survey to start the design.
Budget
Phase | Cost |
---|---|
Design | $181,080.00 |
Construction | $700,000 |
Total Budget | $881,080.00 |
Sidewalk portion will be funded through sales tax
CCUD portion will be funded by the utility
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Planning and Approval | 09/08/2022 | 09/30/2023 | 10/31/2023 |
Design Development | 08/12/2024 | 11/03/2025 | |
Construction | 10/01/2024 | 06/30/2025 | |
Turnover & Closeout | 07/01/2025 | 08/01/2025 |
Project Phase
Design Development
Last Updated
10/17/2024
Project Manager
Raymond Slade
Public Relations
Caitlin Jackson
Email Public Relations
Project Number
2023000366
Sponsor Department
Public Works
Design Engineer/Architect
TBD
Construction Contractor
TBD