Caring Way and Brinson Avenue Sidewalks

Project Description

The project will add two sidewalks, one on Caring Way, from Olean Boulevard to Gertrude Avenue, and one on Brinson Avenue, from Caring Way to Harbor Boulevard. Additionally, the project will incorporate the removal and replacement of any of Charlotte County Utility Department's (CCUD) infrastructure located under or impacted by the future sidewalks.  

The project may be constructed as one or two separate projects, which will be determined before the bid advertisement.

Project Location

Caring Way, from Olean Boulevard to Gertrude Avenue

Brinson Avenue, from Caring Way to Harbor Boulevard

Latest Updates

The PO was issued and the engineer is working on the survey to start the design.

Budget

Phase Cost
Design $181,080.00
Construction $700,000
Total Budget $881,080.00
Funding source(s):

Sidewalk portion will be funded through sales tax

CCUD portion will be funded by the utility 

Schedule

Phase Estimated Start Date Forecast Completion Actual Completion
Planning and Approval 09/08/2022 09/30/2023 10/31/2023
Design Development 08/12/2024 11/03/2025
Construction 10/01/2024 06/30/2025
Turnover & Closeout 07/01/2025 08/01/2025

Project Phase
Design Development

Last Updated
10/17/2024

Project Manager
Raymond Slade

Public Relations
Caitlin Jackson
Email Public Relations

Project Number
2023000366

Sponsor Department
Public Works

Design Engineer/Architect
TBD

Construction Contractor
TBD

Sales Tax Project