Project Description
The county shall construct landscape and irrigation improvements in the median and right of way of CR 771 (Gasparilla Road) between SR 776 and Marathon Boulevard.Project Location
CR 771 (Gasparilla Road) between SR 776 and Marathon Boulevard in both the median and the right of way.Project Impacts
This project experienced delays due to the signalization of the intersection of CR 771 and Marathon Boulevard, Hurricane Ian, Hurricane Milton, and the resulting impact of restoration work on the budget.Latest Updates
Construction is scheduled to begin on May 19th, 2025.Budget
Phase | Cost |
---|---|
Engineering | $60,395.00 |
Construction | $621,829.98 |
Total Budget | $682,224.98 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Construction | 05/19/2025 | 06/23/2025 | |
Turnover & Closeout | 06/16/2026 | 07/01/2026 |
Project Phase
Construction
Last Updated
04/22/2025
Project Manager
Chuck Peters
Public Relations
Chad Ray
Email Public Relations
Project Number
23-335
Sponsor Department
Public Works
Design Engineer/Architect
Johnson Engineering
Construction Contractor
BrightView Landscape Services, Inc