Project Description
Building A sustained heavy damage to its privacy evidence fence, roof, fascia (20 feet), and soffit panels (36 feet). Interior ceilings, walls, floors, doors, trim, furniture, equipment, and contents were water-damaged in multiple rooms. The fire alarm is in trouble mode and requires resetting.
Public Relations:
Project Managers:
- Anthony Altmeyer
- Nicholas Reed
- Joseph Romanelli
Project Location
3110 Loveland Blvd. Port Charlotte, FL 33980Latest Updates
| Description of Work | Estimated Start | Estimated Completion | Storm Event |
|---|---|---|---|
|
Equipment |
Ian | ||
|
Buildings |
Ian |
Budget
| Phase | Cost |
|---|---|
| Total Budget | $230,097.34 |