Project Description
The Conference Center sustained roof damage from a fallen tree on the front right corner, with multiple missing soffit panels, fascia, and a damaged gutter. At the same site, a Finger Pier (100 sq. ft.) and environmental fencing (2,500 linear feet) were damaged. Additionally, a small pier (100 sq. ft.) requires full replacement with design.
Public Relations:
Project Managers:
- Lonne Moore
- Joseph Romanelli
- Travis Purdue
Project Location
2300 Placida Road, Englewood, FL 34224Latest Updates
| Description of Work | Estimated Start | Estimated Completion | Storm Event |
|---|---|---|---|
|
Park Amenities |
Helene | ||
|
Signage |
Helene | ||
|
Fencing |
Ian | ||
|
Sidewalks, boardwalks, piers, dock |
1/11/2023 | 6/11/2027 | Ian, Milton |
|
Buildings |
6/23/2025 | 8/12/2027 | Ian, Milton |
Budget
| Phase | Cost |
|---|---|
| Total Budget | $41,865.22 |