Project Description
The site sustained damage to recreational and park facilities from multiple hurricanes. One playground shade was destroyed, with cables and poles damaged. The restroom building suffered roof, fascia, and soffit damage. Park fencing and a small pavilion were also damaged.
Public Relations:
Project Managers:
- Lonne Moore
Project Location
22410 Glass Lane, Charlotte Harbor, FL 33980Latest Updates
| Description of Work | Estimated Start | Estimated Completion | Storm Event |
|---|---|---|---|
|
Buildings |
Ian | ||
|
Fencing |
Ian | ||
|
Pavilions |
8/4/2025 | 10/31/2025 | Ian |
|
Park amenities |
6/25/2025 | 5/30/2026 | Ian |
Budget
| Phase | Cost |
|---|---|
| Total Budget | $108,000.00 |
FEMA Public Assistance
Insurance