Project Description
Englewood East/Gulf Cove MSBU's have 2 bridges needing design and construction services to implement the FDOT maintenance and repair items for each of the respective bridges. These 2 bridges are shared 50% by each MSBU.
This project is for bridge rehabilitation construction for bridges-
David Blvd. over Newgate Waterway - Bridge #014082
Jennings Blvd. over Lafitte Waterway - Bridge #014088
Project Location
David Blvd. over Newgate Waterway - Bridge #014082
Jennings Blvd. over Lafitte Waterway - Bridge #014088
See Location Map
Latest Updates
This project is complete.
Budget
Phase | Cost |
---|---|
Design | $92,200 |
Construction | $187,416.60 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Planning and Approval | 02/21/2023 | 04/21/2023 | |
Design Development | 05/15/2023 | 02/20/2024 | 02/20/2024 |
Construction | 06/03/2024 | 07/18/2024 | 07/18/2024 |
Supporting Materials
Project Phase
Project Complete
Last Updated
12/10/2024
Project Manager
Kelly Slaughter
Public Relations
Tracy Doherty
Email Public Relations
Sponsor Department
Public Works
Design Engineer/Architect
DRMP Engineering
Construction Contractor
Villa Fuerte Construction