Project Description
Design and construct a new Family Services facility as part of a phased master plan approach. This 2014 Sales Tax Tier 1 project will replace the existing facility with a new code-compliant building. The project is phased combining the adjacent property for a 6 acre site to be masterplanned for future phases. Just over 17,000 square feet the new facility will house Charlotte Counties 211 department. It will have additional space for youth services and community partners to operate from.
The project is the last Tier 1 sales tax project from the 2014 sales tax initiative.
Project Location
21500 Gibraltar Drive, Port Charlotte
Project Impacts
Project remains ahead of schedule and under budget.
Furniture delayed 30 days due to covid and lumber production. No negative impact to the overall project schedule.
Latest Updates
Project Complete
Budget
Phase | Cost |
---|---|
Design | $895,400.00 |
Construction | $7,617,598.00 |
Total Budget | $10,647,000.00 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Planning and Approval | 03/14/2019 | 05/14/2019 | 06/14/2019 |
Design Development | 08/14/2019 | 08/14/2020 | 07/07/2020 |
Construction | 08/24/2020 | 12/31/2021 | 12/17/2021 |
Turnover & Closeout | 08/02/2021 | 02/14/2022 | 03/18/2022 |
Supporting Materials
Project Phase
Project Complete
Last Updated
03/21/2022
Project Manager
Travis Perdue
Public Relations
Brian Gleason
Email Public Relations
Sponsor Department
Human Services
Design Engineer/Architect
Fawley Bryant Architects, Inc.
Construction Contractor
P. J. Hayes INC, DBA: TANDEM Construction