Project Description
The Board of County Commissioners has requested a sidewalk be designed and constructed on Rampart Blvd. as part of the 2020 Sales Tax CIPProject Location
Rampart Blvd. from Luther Rd. to Rio De Janeiro Ave.Latest Updates
The survey is complete and the information is being entered into the 30% plans.Budget
Phase | Cost |
---|---|
Design | $174,930.00 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Planning and Approval | 12/01/2022 |
Project Phase
Design Development
Last Updated
01/13/2025
Project Manager
Raymond Slade
Public Relations
Caitlin Jackson
Email Public Relations
Project Number
c412104
Sponsor Department
Public Works
Design Engineer/Architect
TBD
Construction Contractor
TBD