Road and Bridge FY23 Bridge Rehabilitations - #010061 and #010063

Project Description

These 2 bridges currently require design services to implement the FDOT maintenance and repair items for each of the respective bridges.  

Bridge #010061 is County Road 775 over Buck Creek.

Bridge #010063 is on County Road 775 over Oyster Creek.

Project Location

Bridge #010061 is County Road 775 over Buck Creek.

Bridge #010063 is on County Road 775 over Oyster Creek.

Latest Updates

Project Activities for May 2024

The County has selected Kimley-Horn and Associates as the design firm.

Kimley-Horn has submitted and the County has approved the Bridge Repair Memorandum.  We expect the 60% construction plans for our review on June 28, 2024. 

Budget

Phase Cost
Design $134,865
Funding source(s): Road and Bridge Gas Tax

Schedule

Phase Estimated Start Date Forecast Completion Actual Completion
Design Development 12/14/2023 08/30/2024

Project Phase
Design Development

Last Updated
05/01/2024

Project Manager
Kelly Slaughter

Public Relations
Tracy Doherty
Email Public Relations

Sponsor Department
Public Works

Design Engineer/Architect
Kimley-Horn Engineers