Project Description
This project incorporates the design and construction of new turn lanes at various intersections along Veterans Boulevard. New left and right turn lanes will be added with sidewalk modifications.
Project Location
- Veterans Boulevard @ Atwater Street – East and Westbound right turn lanes
- Veterans Boulevard @ Yorkshire Street – East and Westbound right turn lanes
- Veterans Boulevard @ Harbor Boulevard – East and Westbound right turn lanes
- Veterans Boulevard @ Orlando Boulevard – Eastbound right turn lane
- Veterans Boulevard @ Torrington Street – Eastbound right turn lane
- Veterans Boulevard @ Loveland Boulevard – Eastbound right turn lane
- Veterans Boulevard @ Norman Street – Eastbound right turn lane
Latest Updates
Veterans Boulevard @ Torrington Street intersection. 90% plans are completed. FTE to start final plans.
Veterans Boulevard @ Loveland Boulevard intersection. 90% plans are completed. FTE to start final plans.
Veterans Boulevard @ Yorkshire Street intersection. 90% plans are completed. FTE to start final plans.
Veterans Boulevard @ Harbor Boulevard intersection. 90% plans are completed. FTE to start final plans.
Veterans Boulevard @ Orlando Boulevard intersection. 90% plans are due for review on September 23, 2024
Veterans Boulevard @ Atwater Street intersection. Design survey has started. 60% plans are due for review on September 16, 2024
Veterans Boulevard @ Norman Street intersection. Design survey has started. 60% plans are due for review on October 14, 2024
Budget
Phase | Cost |
---|---|
Design | $813,637.50 |
Construction | $2,579,754.16 |
Total Budget | $3,393,391.66 |
Gas Tax C411620
State Funded Grant
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Planning and Approval | 02/11/2019 | 08/14/2019 | 08/14/2019 |
Design Development | 09/02/2020 | 12/15/2024 | |
Construction | 10/21/2024 | 07/25/2025 |
Supporting Materials
Project Phase
Design Development
Last Updated
09/03/2024
Project Manager
Jeff Keyser
Public Relations
Tracy Doherty
Email Public Relations
Project Number
19-279
Sponsor Department
Public Works
Design Engineer/Architect
Florida Transportation Engineering
Construction Contractor
TBD