A Design/Build contract with Magnum Builders to construct a new Fire Station 10. The building program shall consist of the following elements, new two bay fire station; space to accommodate up to five staff when required; a small training area and a stand-by generator system.Project Location
71 Gasparilla Way (Don Pedro Island) Placida, FloridaProject Impacts
NoneLatest Updates
The new station is in operation. Please contact Todd Dunn (PIO) at 941-833-5610 for more information.Budget
| Phase | Cost |
|---|---|
| Design | $398,757.00 |
| Construction | $3,373,737.00 |
| Other Costs | $143,010 |
| Total Budget | $3,915,504.00 |
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Planning and Approval | 05/30/2019 | 09/20/2019 | 11/12/2019 |
| Design Development | 07/08/2019 | 07/08/2020 | 07/31/2020 |
| Construction | 10/30/2020 | 02/02/2022 | 02/02/2022 |
| Turnover & Closeout | 02/02/2022 | 02/10/2022 | 02/10/2022 |
Supporting Materials
Project Phase
Completed 04/21/2023
Project Number
c221901
Sponsor Department
Public Safety
Design Engineer/Architect
Sweet - Sparkman Architects
Construction Contractor
Magnum Builders