Project Description
Design and construct a sidewalk on Fruitland Avenue and Avenue of the Americas.Project Location
Fruitland Avenue from Winchester Boulevard to Gulfstream Boulevard and Avenue of the Americas from San Casa Drive to Winchester Boulevard.Latest Updates
The Avenue of the Americas / Fruitland sidewalk construction has started with the contractor on Fruitland Ave. clearing, grading and pouring concrete after Fruitland is done they will move to the Ave. of the Americas side of the project.Budget
Phase | Cost |
---|---|
Design | $170,960.30 |
Construction | $714,000.00 |
Total Budget | $884,960.30 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Planning and Approval | 10/01/2021 | 11/30/2021 | 03/22/2022 |
Design Development | 03/23/2022 | 11/18/2023 | 12/28/2023 |
Construction | 06/03/2024 | 01/01/2025 |
Project Phase
Construction
Last Updated
08/27/2024
Project Manager
Raymond Slade
Public Relations
Tracy Doherty
Email Public Relations
Project Number
c412104.41421
Sponsor Department
Public Works
Design Engineer/Architect
TBD
Construction Contractor
TBD