Project Description
Design and construct a pathway on Gasparilla Pines Boulevard
Project Location
Gasparilla Pines Boulevard from Placida Road (CR 775) to the end of road at the Amberjack Environmental Park.Latest Updates
The 100% plans were received and are under review by staff. The approved SWFWMD exemption was received. The MSBU committee has requested to push construction out to FY 26 to avoid having to rase the assment for funding, the plans will be finished and the project will be tabled for further direction.Budget
Phase | Cost |
---|---|
Design | $116,900.00 |
Construction | $611,000.00 |
Total Budget | $727,900.00 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Design Development | 03/03/2022 | 03/01/2023 | |
Construction | 01/01/2026 | 07/01/2026 |
Project Phase
Planning and Project Approval
Last Updated
09/17/2024
Project Manager
Raymond Slade
Public Relations
Tracy Doherty
Email Public Relations
Sponsor Department
Public Works
Design Engineer/Architect
Johnson Engineering
Construction Contractor
TBD