Project Description
Design and construct a pathway on Gasparilla Pines Boulevard.
Project Location
North side of Gasparilla Pines Boulevard from Placida Road (CR 775) to the end of road at the Amberjack Environmental Park.Latest Updates
The 100% plans and bid package were received . The approved SWFWMD exemption was received. The construction funding of this project was not approved it will be put on hold for future funding.Budget
Phase | Cost |
---|---|
Design | $116,900.00 |
Construction | $1,300,000.00 |
Total Budget | $1,416,900.00 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Design Development | 03/03/2022 | 03/01/2023 | 03/01/2023 |
Construction | 01/01/2026 | 07/01/2026 |
Project Phase
Planning and Project Approval
Last Updated
08/25/2025
Project Manager
Raymond Slade
Public Relations
Chad Ray
Email Public Relations
Sponsor Department
Public Works Engineering
Design Engineer/Architect
Johnson Engineering
Construction Contractor
TBD