Project Description
The Gulf Cove Street and Drainage MSBU requested to design & construct 6' sidewalks on the south side of David Boulevard, the south side of Gillot Boulevard, the north side of Foresman Boulevard & the west side of Holton Terrace.Project Location
Design & Construct 6' sidewalks on
- David Boulevard from Holton Terrace to Foresman Boulevard
- Gillot Boulevard from SR 776 to David Boulevard
- Foresman Boulevard from David Boulevard to Holton Terrace
- Holton Terrace from Foresman Boulevard to David Boulevard
Project Impacts
Funding for this project was pushed out to FY26 for Phase 1. Gillot Blvd. SR776 to David Blvd.Latest Updates
-
The 100% construction plans for David Boulevard, Gillot Boulevard, Holton Terrace, and Foresman Boulevard have been received.
-
Construction has been deferred until FY28 to allow for completion of the SunTrail project.
Budget
| Phase | Cost |
|---|---|
| Design | $247,913.15 |
| Construction | $4,510,000.00 |
| Total Budget | $4,757,913.15 |
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Design Development | 06/20/2018 | 07/31/2019 | 07/31/2020 |
| Construction | 10/29/2027 | 07/28/2028 |
Project Phase
Design Development
Last Updated
03/02/2026
Project Manager
Raymond Slade
Public Relations
Chad Ray
Email Public Relations
Sponsor Department
Public Works
Design Engineer/Architect
Johnson Engineering / Southwest Engineering
Construction Contractor
TBD