Project Description
The Gulf Cove Street and drainage MSBU requested to design & construct 6' sidewalks on the south side of David Boulevard, the south side of Gillot Boulevard, the north side of Foresman Boulevard & the west side of Holton Terrace.Project Location
Design & Construct 6' sidewalks on
- David Boulevard from Holton Terrace to Foresman Boulevard
- Gillot Boulevard from SR 776 to David Boulevard
- Foresman Boulevard from David Boulevard to Holton Terrace
- Holton Terrace from Foresman Boulevard to David Boulevard
Project Impacts
Funding for this project was pushed out to FY23 for phase 1. The MSBU committee decided to wait until the community plan is finished before moving forward with any one project.Latest Updates
100% plans for David Boulevard, Gillot Boulevard, Holton Terrace, and Foresman Boulevard were received. Construction was pushed until FY24.Budget
Phase | Cost |
---|---|
Design | $247,913.15 |
Construction | $4,510,000.00 |
Total Budget | $4,757,913.15 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Design Development | 06/20/2018 | 07/31/2019 | 07/31/2020 |
Project Phase
Planning and Project Approval
Last Updated
09/17/2024
Project Manager
Raymond Slade
Public Relations
Tracy Doherty
Email Public Relations
Sponsor Department
Public Works
Design Engineer/Architect
Johnson Engineering / Southwest Engineering
Construction Contractor
TBD